Harlingen city commissioners rejected a proposed drainage agreement with Cameron County on Oct. 21 after discovering provisions concerning Fluidstack's data center development that went beyond flood control.

The agreement would have established a framework for cooperation on drainage improvements associated with the company's multibillion-dollar data center campus outside Harlingen.

During the Oct. 21 City Commission meeting, Commissioner Rene Perez questioned language requiring the city to process requests involving its extraterritorial jurisdiction and help facilitate consideration of wastewater service requests for Fluidstack properties.

The proposed agreement had not been included in the publicly available agenda packet, and commissioners received copies during the meeting.

City Manager Gabriel Gonzalez acknowledged the omission.

Commissioners question additional provisions

The agreement was presented as an interlocal arrangement for drainage maintenance and flood control.

However, Article 3 included provisions addressing Fluidstack's development.

One section called for Harlingen to promptly process petitions seeking to remove Fluidstack-related properties from the city's extraterritorial jurisdiction, or ETJ.

Another called for the city to support and facilitate Harlingen WaterWorks System's consideration of requests for wastewater service.

The provisions did not automatically approve those requests or guarantee wastewater service, but they raised concerns about the scope of the proposed agreement.

Perez questioned why the county was seeking commitments involving the developer's properties through a drainage agreement.

He argued that Fluidstack should negotiate directly with Harlingen rather than through Cameron County.

Other commissioners expressed concerns about reviewing the agreement without sufficient advance notice.

County representatives described the proposal as a preliminary framework that would require further legal, engineering and administrative review before specific improvements could proceed.

Drainage improvements remain under discussion

The proposed agreement followed earlier discussions involving Fluidstack, Cameron County and the City of Harlingen.

According to a Nov. 4 report by the Rio Grande Valley Business Journal, a previously discussed public-private partnership included a proposed $20 million community-benefits contribution and $7 million in drainage improvements near Valley International Airport.

That arrangement did not move forward.

The drainage improvements were intended to address stormwater runoff from the data center development, which is being built outside Harlingen's city limits.

Fluidstack has sought permission to discharge stormwater into the city-owned Airport Lateral drainage system.

Cameron County Commissioners Court had previously voted Oct. 6 to advance a proposed interlocal agreement, subject to legal review.

The Harlingen commission declined to approve the county's framework.

City seeks direct talks and public meeting

Mayor Norma Sepulveda told commissioners she had contacted Fluidstack about a public town hall that city officials had previously requested.

According to the mayor, the developer committed to holding that meeting before the end of November, with or without direct city participation.

Commissioners indicated they wanted the company to answer residents' questions about the development and negotiate directly with Harlingen on infrastructure needs.

The commission's rejection left the proposed drainage arrangement unresolved.

It did not cancel the data center or revoke construction-related authorizations issued by Cameron County.

Data center construction continues

Fluidstack announced in September that work had begun on the first phase of its planned $4 billion data center development between Harlingen and Rio Hondo.

The project involves more than 1,100 acres in unincorporated Cameron County, near Valley International Airport.

The initial development is planned to support up to 1.5 gigawatts of computing infrastructure.

Cameron County issued a worksite permit Sept. 10 authorizing preliminary activities, including land clearing, grading and utility installation.

Additional permits are required for building construction.

The proposed connection to Harlingen's drainage infrastructure remains a separate issue requiring further agreement and approvals.