Harlingen commissioners are scheduled to reconsider a street-paving materials bid Wednesday, Nov. 18, after higher asphalt costs threatened the city's plan to improve nearly 15 miles of roads.

The City Commission tabled the bid Nov. 4 while officials discussed reducing the paving program or using additional city funds to preserve more of the planned improvements, according to the city's meeting recording.

The proposed changes could affect streets selected for paving across Harlingen's five commission districts.

Asphalt costs threaten paving plans

Commissioners previously approved plans to pave 14.9 miles of streets as part of the annual improvement program, myRGV reported Nov. 10.

City Engineer Robert Hernandez told commissioners that asphalt bids had risen to approximately $82 per ton, compared with $72 per ton the previous year.

The higher material costs created a funding gap that prompted officials to reconsider how many miles they could afford to pave.

City officials said completing the full program would require additional funding beyond the amount initially available.

Options for covering the difference

During the Nov. 4 discussion, staff outlined several alternatives for the 2027 street improvement program.

One option would reduce the paving program to approximately 12.1 miles while using $600,000 from an existing street improvement account and another $600,000 from the general fund.

Completing the approximately 15-mile program would require a larger draw on city reserves.

Officials estimated that the full program would exceed the available paving budget by about $1.8 million. After accounting for money already available in the street improvement fund, the city would need approximately $1.2 million more from the general fund balance.

Commissioners discussed whether they should reduce paving in each district or use additional reserves to preserve the original street list.

Commissioners question cost estimates

Commissioner Daniel Lopez questioned why commissioners learned about the higher asphalt costs after previously approving the street program.

Hernandez explained that the city typically identifies streets for improvements before seeking formal material bids. Those bids establish the prices needed to award contracts.

Mayor Norma Sepulveda also questioned whether preliminary price estimates could have given commissioners a better understanding of the likely costs.

City officials noted that Harlingen has reduced paving expenses by using its own public works crews rather than relying entirely on contractors.

However, the city still must purchase asphalt and other materials, leaving the program exposed to higher prices.

Bid returns for consideration

The Nov. 18 City Commission agenda lists Bid No. 2027-01, covering materials for the 2027 Street Improvement Project, for possible approval.

The agenda identifies the item as previously tabled at the Nov. 4 meeting.

Commissioners could consider awarding the materials contract as they determine how to fund the paving program and whether to reduce the planned work.

The meeting is scheduled for 5:30 p.m. at City Hall, 118 E. Tyler Ave.

The number of miles to be paved and any additional funding remain unresolved in the reviewed Nov. 4 decision record.